23 Webb Street

August 28, 2025

We’re pleased to share that construction at 23 Webb Street is progressing well. Water, power, and drainage connections have now been completed on site, and the concrete foundations are in place, providing a solid base for the build. Work has also begun on the concrete block ITC walls, marking an exciting step as the structures start to emerge above ground level. We’ll continue to provide progress updates approximately every two weeks to keep you informed as the build advances through each stage. Thank you for being part of this journey.