canopy-deans-avenue
Back to updates
Canopy Deans Avenue

October 11, 2026

Construction Update

Great progress continues across the development, with several key milestones achieved and more exciting work scheduled over the coming weeks.

  • Blocks C & D: Timber piling is now complete, with foundation works and concrete slab preparation set to commence next week.
  • Civil Works: Drainage works are well underway across the site.
  • Roading & Access: Chip sealing of the new road and car parking areas is scheduled for next week, alongside the formation of the new entrance off Deans Avenue.
  • Blocks A & B: Stone piling is scheduled to commence on 16 October.

It's great to see the development taking shape as work progresses across multiple areas of the site.

‍

No items found.

Other Updates