Construction is progressing well at Naseby Street, with the ground floor framing now complete and floor joists currently being installed.
The first floor framing is scheduled to arrive on Tuesday 30 June, marking another exciting milestone as the homes continue to take shape. Roof trusses are booked for delivery on Monday 6 July, with roofing works expected to follow shortly after.
We're on track to have the development under roof by around 16 July, bringing us another step closer to completion. Stay tuned for more updates as progress continues.