Progress continues steadily across the site as areas begin transitioning from finishing works to final detailing.
- Block A: Interior painting is complete, and 50% of kitchens are now installed.
- Block B: Plumbing and electrical fit-offs are complete, and carpet installation has been completed.
- Block D: Kitchens are installed, plumbing and electrical fit-offs are approximately 50% complete, and carpet installation is underway in completed units.
- Blocks G and H: Carpet is installed, and final defect checks are currently underway.
The site is continuing to develop well, with each area progressing steadily through its respective stages.