888-colombo-street
Back to updates
888 Colombo Street

November Build Update

November 17, 2025

Progress continues steadily across the site as areas begin transitioning from finishing works to final detailing.

  • Block A: Interior painting is complete, and 50% of kitchens are now installed.
  • Block B: Plumbing and electrical fit-offs are complete, and carpet installation has been completed.
  • Block D: Kitchens are installed, plumbing and electrical fit-offs are approximately 50% complete, and carpet installation is underway in completed units.
  • Blocks G and H: Carpet is installed, and final defect checks are currently underway.

The site is continuing to develop well, with each area progressing steadily through its respective stages.

‍

No items found.

Other Updates