Progress is moving along well across the site.

  • Blocks B and I: Plumbing and electrical fit-offs are underway.
  • Block D: Tiling and painting are progressing, with kitchen installations and a range of carpentry work also taking place.
  • Blocks H and I: Decking and landscaping are being completed.
  • Block B: Decking and landscaping are now getting underway.

It’s great to see the development taking shape as we move through these final stages.